Development of a Machine Learning-Based DSS for Predicting Unit Price Escalation of Water Resources Projects: Literature Review

Authors

  • Ince Suil Febryan Maula Civil Engineering Doctoral Program, Faculty of Engineering, Universitas Tarumanagara, Jakarta Barat 11440, Indonesia;ince.328242010@stu.untar.ac.id
  • Lina Lina Civil Engineering Doctoral Program, Faculty of Engineering, Universitas Tarumanagara, Jakarta Barat 11440, Indonesia;ince.328242010@stu.untar.ac.id
  • Endah Murtiana Sari Industrial Engineering, Universitas Sains Indonesia, Bekasi, Indonesia

DOI:

https://doi.org/10.51988/jtsc.v7i3.646

Keywords:

Decision Support System, Machine Learning, unit price escalation, water resources project, cost prediction

Abstract

Unit price escalation in Water Resources (SDA) projects is a challenge for project implementation success. The uncertainty of material prices, labor wages, equipment costs, energy prices, inflation, exchange rates, changes in government policies, spatial conditions, project characteristics, and various external risks make price escalation predictions increasingly complex and difficult to perform using conventional approaches. The development of ML combined with DSS offers a more adaptive, accurate, and data-driven predictive approach to support decision-making  of projects. This study aims to examine the application of ML in predicting unit price escalation in SDA projects, identify factors that influence prediction accuracy, and formulate directions for integrated DSS development. The study uses the Systematic Literature Review (SLR) method based on the PRISMA 2020 guidelines by reviewing articles published in the period 2015–2025 from the Scopus, Web of Science, ScienceDirect, IEEE Xplore, and SpringerLink databases. The results of the study indicate that the Random Forest, Extreme Gradient Boosting (XGBoost), Artificial Neural Network (ANN), Long Short-Term Memory (LSTM), and Gradient Boosting algorithms provide better predictive performance than conventional statistical methods. Most studies are still oriented towards general project cost estimation and have not developed a DSS capable of dynamically integrating economic factors, labor, project characteristics, spatial conditions, risks, and historical data to predict unit price escalation of natural resource projects. 

References

P. E. D. Love, J. Matthews, W. Fang, and H. Mahamivanan, “Integrating Evidence into the Design of Explainable Artificial Intelligence and Decision Support Systems: A Means-End Framework for End-users in Construction,” 2021.

T. P. Nguyen and N. Chileshe, “Revisiting the construction project failure factors in vietnam,” Built Environment Project and Asset Management, vol. 5, no. 4, pp. 398–416, Sep. 2015, doi: 10.1108/BEPAM-10-2013-0042.

P. E. D. Love, P. Teo, and J. Morrison, “Revisiting Quality Failure Costs in Construction,” J. Constr. Eng. Manag., vol. 144, no. 2, Feb. 2018, doi: 10.1061/(asce)co.1943-7862.0001427.

S. D. Datta, “Artificial Intelligence and Machine Learning Applications in the Project Lifecycle of the Construction Industry: A Comprehensive Review,” Artificial Intelligence and Machine Learning Applications in the Project Lifecycle of the Construction Industry: A Comprehensive Review, vol. 10, 2024.

S. Al-Gahtani, “ANN Prediction Model of Final Construction Cost at an Early Stage,” Journal of Asian Architecture and Building Engineering, vol. 24, no. 2, pp. 775–799, 2025.

M. O. Sanni-Anibire, “Machine Learning-Based Framework for Predicting Cost and Schedule Performance of Construction Projects,” Journal of Information Technology in Construction, vol. 26, pp. 337–359, 2021.

S. Banihashemi, “Machine Learning-Integrated 5D BIM Informatics: Building Materials and Construction Cost Estimation,” Innovative Infrastructure Solutions, vol. 7, 2022.

G. H. Coffie, “Using Extreme Gradient Boosting Machine Learning and SHAP to Predict Construction Project Cost Overruns,” International Journal of Construction Management, 2024.

M. Shafaay, “Modeling Construction Cost-Overrun Risks at the Front-End Engineering Design Stage,” Journal of Asian Architecture and Building Engineering, 2025.

Y. Jezzini, “Risk Allocation Model for Price Escalations in Construction Projects Using Game Theory,” Risk Allocation Model for Price Escalations in Construction Projects Using Game Theory, 2025.

M. Aslam, Z. Gao, and G. Smith, “Exploring factors for implementing lean construction for rapid initial successes in construction,” J. Clean. Prod., vol. 277, Dec. 2020, doi: 10.1016/j.jclepro.2020.123295.

Z. Qadeer, N. A. Memon, M. A. Leghari, A. H. Memon, and F. H. Siddiqui, “Identification of Critical Factors Influencing Cost Escalation In Public Sector Construction Projects,” 2019.

C. H. M. P. and C. A. H. H. Yoon, “Construction Cost Index Forecasting through Multivariate Time-Series Modeling and Leading Indicators,” Journal of the Architectural Institute of Korea, vol. 41, no. 5, pp. 319–329, 2025.

G. Coffie and S. Cudjoe, “International Journal of Construction Management ISSN: (Print) ( Using extreme gradient boosting (XGBoost) machine learning to predict construction cost overruns Using extreme gradient boosting (XGBoost) machine learning to predict construction cost overruns,” Jul. 2023. doi: 10.1080/15623599.2023.2289754.

“The PRISMA 2020 statement: An updated guideline for reporting systematic reviews,” BMJ, 372, n71, pp. 1–72, 2021.

M. G. Meharie, Z. C. A. Gariy, R. N. Ndisya Mutuku, and W. J. Mengesha, “An Effective Approach to Input Variable Selection for Preliminary Cost Estimation of Construction Projects,” Advances in Civil Engineering, vol. 2019, 2019, doi: 10.1155/2019/4092549.

C.-H. Huang and S.-H. Hsieh, “Predicting BIM Labor Cost with Random Forest and Simple Linear Regression,” Autom. Constr., vol. 18, 2020.

D. Chakraborty, H. Elhegazy, H. Elzarka, and L. Gutierrez, “A novel construction cost prediction model using hybrid natural and light gradient boosting,” Advanced Engineering Informatics, vol. 46, p. 101201, 2020, doi: https://doi.org/10.1016/j.aei.2020.101201.

P. Karadimos and L. Anthopoulos, “A Taxonomy of Machine Learning Techniques for Construction Cost Estimation,” Innovative Infrastructure Solutions, vol. 9, 2024.

F. Xiao, X. Chen, S. Yang, and J. Cheng, “Bi-objective pavement maintenance and rehabilitation optimization decision-making model incorporating the construction length of preventive maintenance projects,” Structure and Infrastructure Engineering, vol. 21, no. 1, pp. 24–38, 2025.

H. H. Elmousalami, “Artificial Intelligence and Parametric Construction Cost Estimate Modeling: State-of-the-Art Review,” J. Constr. Eng. Manag., vol. 146, no. 1, Jan. 2020, doi: 10.1061/(asce)co.1943-7862.0001678.

J. Cranefield and P. Yoong, “The Electronic Journal for Virtual Organizations and Networks Organisational Factors Affecting Inter-Organisational Knowledge Transfer In The New Zealand State Sector: A Case Study,” 2005.